Ratlam (Rep. of New Zealand). A large number of works have been approved by the Municipal Corporation in the city, but the work is not visible, all the engineers and contractors should ensure that the approved work starts by Saturday, otherwise the contractor’s earnest money will be confiscated and blackened. will be listed. Collector Kumar Purushottam gave these instructions to the contractors of the Municipal Corporation in the meeting.
Municipal Commissioner Somnath Jharia, Executive Engineer Mohammad Hanif Sheikh, Sureshchandra Vyas, Assistant Engineer Shyam Soni etc. were present in the meeting organized in the Civic Center meeting room. In the meeting, while reviewing the works of the Municipal Corporation for road, drain, paver construction, etc., the Collector said that those contractors who have been issued work orders, but the contract has not been signed, will have to edit the contract and start work in two days. On Saturday, the inspection will be done by the collector himself. On that day, along with the sub-engineer, the contractor was also present at the site.
Status of construction works in the city
Road under construction: CC road from Morning Star School to Tanker Road, asphaltization on Inderlok Nagar main road, CC construction near Dongre Nagar water tank, asphaltization from Jawahar Nagar Muktidham to Devra Devnarayan via Guru Ramdas.
Work order issued: Asphaltization from Vinoba Nagar tank to Globus gate, asphaltization on Jai Baba school road, construction of asphalt road from Ambe Mata Chowk to Sai Building via Radhe Krishna temple and asphaltization work from 80 feet road to Ratnapuri. have been given.
Work Completed: Construction of CC road from Suyog Complex to PMAY Building Mukherjee Nagar, CC road construction from Padmashree Bar Sailana Road to Kasturba Nagar street number 6 and CC road from Rocket Laundry to Arogya Hanuman Mandir have been completed.
Approval is yet to be taken: from Dalu Modi Bazar to Ganesh Deori, from Raniji’s temple to Hardev Lala’s generation, from Rani Ji’s temple to Naharpura square, Neem Chowk, Manak Chowk area, Dalu Modi Bazar to Ghas Bazar, Bajaj Khana Road However, approval is pending for asphaltization and installation of paver blocks from Chandni Chowk to Ghas Bazar, from Shaheed Chowk to Rani ji’s temple and Ganesh Deori.
Posted By: Nai Dunia News Network